Dear All,

how to schedule the outerbox reports(Overview Reports) to send to a particular person?.

Thanks,
VeerRaju.

 

 

P.S. This thread has been moved from Application Perf Mgmt (BAC / BSM) Support and News Forum to CMS and Discovery Support and News Forum. - Hp Forum moderator

17 REPLIES
Arvind Kumar
Occasional Visitor
Solution

Re: Scheduling the reports

Hi,

Can you more clear on the above query where you are using to send this reports from sitescope or BAC.
VeerRaju
Collector

Re: Scheduling the reports

Dear Arvind,

I am trying to schedule the outer box reports that are available in UCMDB(Over View Reports).

So please suggest me how can I schedule the outer box reports in UCMDB and needs to send an email also automatically?.

Thanks,
VeerRaju.
VeerRaju
Collector

Re: Scheduling the reports

Hi Arvind,

Please let me know if you need any additonal information?.

Thanks,
VeerRaju.
Anjeneya.dubey
Frequent Visitor

Re: Scheduling the reports

Goto admin UCMDB>settings>scheduler . here you cn schedule all your reports.
VeerRaju
Collector

Re: Scheduling the reports

Hi Anjaenaya,

Could you please elaborate little bit more as I never scheduled the reports in UCMDB?.

More over, I need to send to the report automatically to the specified reciepents?.

Thanks,
VeerRaju.
Anjeneya.dubey
Frequent Visitor

Re: Scheduling the reports

first create a report eg:gold master report. then go to scheduler and in action select the gold master report and select the schedule
VeerRaju
Collector

Re: Scheduling the reports

Hi Anjenaya,

We are using outerbox reports to schedule. We have overview reports and needs to schedule those over view reports.

so please suggest us how can we schedule the outerbox reports?.

It would be great if you shares the screenshots with us?.

Thanks,
VeerRaju.
VeerRaju
Collector

Re: Scheduling the reports

Hi Anjenaya,

Thanks for your prominent reply. But Actually we are planning to schedule the overview reports like OS breakdown, Database Breakdown and so on. Basically these reports appears in the form of charts.

So We are planning to schedule these reports and needs to send to reciepent.

Please suggest us how can we schedue the outerbox overview reports?.

Thanks,
VeerRaju.
Anjeneya.dubey
Frequent Visitor

Re: Scheduling the reports

these reports are generated only at the time of viewing. You cna try by saving that report in report repository. you have that option at the right corner where you have options export to csv, xl etc. once it is saved to report repository you can probably schedule it. but you wont be having full flexibility.
VeerRaju
Collector

Re: Scheduling the reports

Hi Anjenaya,

Could you please explain little bit more as I have not worked much on reports?.

But is these reports will appear in the Scheduler?.

Thanks,
VeerRaju.
Anjeneya.dubey
Frequent Visitor

Re: Scheduling the reports

these reports can be generated only at the time of viewing. I dont think it can be scheduled but you can have them in your report repository so that you dont have to create the reports everytime.
VeerRaju
Collector

Re: Scheduling the reports

Hi Anjenaya,

But,I have to schedule these outerbox reports?.

Do you know any other procedure to schedule the outer box reports?.

Thanks,
VeerRaju.
Anjeneya.dubey
Frequent Visitor

Re: Scheduling the reports

as i said i dont think if you can schedule the OOB reports from uCMDB. What version of uCMDB are you using. Is it integrated with BAC?
VeerRaju
Collector

Re: Scheduling the reports

Hi Anjenaya,

We are using UCMDB 7.5.1.

Thanks,
VeerRaju.
Christopher Car
Senior Member

Re: Scheduling the reports

I am running uCMDB 8.02 and I would like to know how I can automatically generate a gold master report and have it emailed at a specified interval (i.e. monthly). From what I can see from the past thread and from the scheduler options, I don't see a way to do this. I can't imagine that the uCMDB doesn't have an automated way for me to run a gold master report and have it emailed automatically. Let me know!

Thanks,
Chris
Alexander Arkhi
Honored Contributor

Re: Scheduling the reports

Chris,

Re GoldMaster reports - try to do the following:
* Create & Generate GoldMaster Report
* Create "Favorite Filter" out of that report
* Navigate to Application -> Reports -> Report Manager
* Create a schedule there using the Favorite Filter you just defined
* Enjoy :)

Regards,
Alex
Ms Black
Regular Collector

Re: Scheduling the reports

Hi VeerRaju,

We can schedule the reports.
The way by which we can do is by craeting a filter.
The filter can be seen in Reports->ReportManager.
Here you can schedule that report.