Is Free Day taken into account for deadline calculation..?

Highlighted
veeratee
Super Collector

Is Free Day taken into account for deadline calculation..?

Hi,

I have a question regarding the Free Day is it taken into account when calculate the deadline i.e. when the deadline calculation is on 4/4/07 and actually this date is specified in the free day, Is the system move to the next day(5/4/07)...?

My environement: HPOVSD 4.5 with SP9

Regards,
Veerat.
3 REPLIES
Mike Bush
Honored Contributor

Re: Is Free Day taken into account for deadline calculation..?

yes
Pinion
HPE Expert

Re: Is Free Day taken into account for deadline calculation..?

Solved in Service Desk 4.5 SP12

Regards,
Kriengsak L
-/\-