Quality Center / ALM Practitioners Forum
cancel

Migration: Test Director -> QC 9.2 -> ALM

Highlighted
sriabarna
Regular Contributor.

Migration: Test Director -> QC 9.2 -> ALM

 

 

Hi...

 

We are planning to migrate from Test director to HP ALM.

 

I want to know, whether directly from Test Director to ALM can be migrated? Or I have to migrate to QC 9.2 and then to HP ALM?

 

Please clarify me. Also please let me know, if my above approach is wrong.

 

thanks....

1 REPLY
Trudy Claspill
Acclaimed Contributor.

Re: Migration: Test Director -> QC 9.2 -> ALM

The minimum version for projects that ALM v11 Site Admin can upgrade is Quality Center 9.2. Anything older than that (QC 9.0 QC 8.x, TestDirector) must first be upgraded to QC 9.2.
[If this post solves or helps solve your issue, mark the thread as solved and give KUDOS to the author for their assistance.]

(Opinions expressed in my postings are mine alone, and do not reflect the opinions of my employer.No warranties express or implied for any solution/suggestion posted.)