Hi All,

Is there anyway we can sync Staffing profile actual hours with the financial summary cost data.

We found that staffing profile actual hours does not synch with the financial summary. We are using PPM 9.3 version.

Could you please anyone advice whether this option available or not in configuration in any way.


Best Regards,
Shravan

1 REPLY
Benny Kung
Contributor.

Re: staffing profile actual hours does not synch with the financial summary

This is not an available option. PPM only enables the synch for timesheets and workplans.