resource effort assignment on a task

Highlighted
marcocattarin
Occasional Advisor

resource effort assignment on a task

How it is possible to split the resource's effort allocation upon a single project task by months? For example: on a task with duration 2 months I need to allocate a resource 10 days on the first month nd 20 days on the second month.
marco.cattarin@txt.it
1 REPLY
Semenov Alexand
Esteemed Contributor

Re: resource effort assignment on a task

Good Day.
We have a same problem but in PPM it's impossible. Workaroun-creating same task with name + 1 for variouse periods.
We open ER in HP-Waiting!!!
Good Luck
//Add this to "OnDomLoad" event