Dear guys,

we are planning to upgrade the PPMC from 7.1 to 8.x. But we should do the upgrade process parallel with a platform change from hp-ux to windows.

What is supported/suggested order to do it, pros and cons?I mean first upgrade then migrate OR first migrate then upgrade?

Any experience regarding changing platform from unix to ms would be welcome.

I really appreciate your help!
Cheers,
Zoltan

2 REPLIES
Volker Schoettn
Honored Contributor.

Re: migrating and upgrading PPMC

Hi,

finally it is up to you. The only advantage, I can see, in first move to windows is: You will have a nice gui for the upgrade...

I have moved PPM from Linux to windows a couple of time with no problems.

Regards
Volker
Surendra Poosar
Honored Contributor.

Re: migrating and upgrading PPMC

Hi Volker,

Did you see any difference in the performance when you have migrated PPM from Windows to Linux?
How complicated is it to do the migration. Do you have some document to state the sequence of steps to migrate PPM from Windows to Linux.

Thanks
Surendra.