lock down tasks in a workplan

Highlighted
bhanu2507
Contributor.

lock down tasks in a workplan

Hi,

 

Is there a way I can lock down the main tasks in a workplan? In the sense, PM can create/modify the sub-tasks but should not be able to add/modify main tasks.

 

Regards

1 REPLY
Celil
Acclaimed Contributor.

Re: lock down tasks in a workplan

Hi,

 

if you restrict PM permissions, who manage whole projects ?

 

There is a solution but it isn't limit PM. 

PM manage whole project and he/she can assign a responsible person to a task. The responsible can add/remove/edit sub tasks or assign resources (briefly can manage) his/her task. In this solution, the task name is Summary Task, the responsible name is Summary Task Owner. 

 

PS: If the post resolves your issue, please click KUDOS star icon and mark it as Accepted Solution.

 

Celil

IT Governance Professional