how to pass the sysdate in Baseline creation of WorkPlan

SOLVED
Go to solution
Highlighted
Nimmakayala
Occasional Contributor

how to pass the sysdate in Baseline creation of WorkPlan

Hi Team,

I have an requirement that need to pass the sysdate while creating the baseline for Workplan.

Could any one pleas help me to fix this.

ksc_create_baseline BASELINE_NAME="Baseline 'sysdate' " like this way i need it

Regards,

Praveen.

1 REPLY
Nimmakayala
Occasional Contributor
Solution

Re: how to pass the sysdate in Baseline creation of WorkPlan

I have got the solution for this command.

ksc_create_baseline BASELINE_NAME="Baseline [SYS.ITG_TIME_STAMP]"

 

Regards,

Praveen.

//Add this to "OnDomLoad" event