how to calculate SPI, CPI values in PPM

Highlighted
riznad
Super Contributor.

how to calculate SPI, CPI values in PPM

Hello;

Is there any guide for calculating Schedule Performance Indicator (SPI) and cost performance index  CPI in PPM?

Which fields should I fill?

Which configurations should I make?

Is there some one who is using those indicators?

 

Regards

 

1 REPLY
Celil
Acclaimed Contributor.

Re: how to calculate SPI, CPI values in PPM

Hi Riznad,

 

  1. activate project financial settings at project settings. all cost must be calculated over work plan
  2. assign all resources a cost rate from financial management at administration menu
  3. work plan must have schedule and actual data. (actuals can come from time sheets)
  4. baselines must be taken
  5. check shedule jobs of server. project metrics and project financials jobs must be run

 

PS: If the post resolves your issue, please KUDOS the professionals and mark it as Accepted Solution.

 

Celil

IT Governance Professional
& PPM Solution Architect