how it is computed the "percent complete" in project's gantt?

Highlighted
marcocattarin
Occasional Advisor

how it is computed the "percent complete" in project's gantt?

Hello,
on each task the indication of % complete is indicated by the resource for that task.
PPM is reporting automatically this percentage through tasks levels, from bottom to up, until to the project level0 task.
The way that PPM is using to compute upper level tasks percentage is not clear to me ???
thanks
2 REPLIES
Erik Cole_1
Esteemed Contributor

Re: how it is computed the "percent complete" in project's gantt?

marcocattarin
Occasional Advisor

Re: how it is computed the "percent complete" in project's gantt?

thanks.
I was quite new of the forum. I was satisfied by your link.