Project and Portfolio Management Practitioners Forum
cancel

holiday definiations in task

Highlighted
eata
Super Contributor.

holiday definiations in task

Case details
Hello;
In our regional calender 23th of april is defined as holiday.

Weekends are holidays also. Weekends are recognized as holidays. In a task,for example, when holidays are included in an interval the system adds working days at the end of the interval. When I select thursday as start date and 5 days as task duration days, the end date of task become wednesday of the next week (task_duration_right). But when I select 20.04.2012 as start date and 5 days as task duration finish date should be 27.04.2012 (because 23.04.2012 is national holiday defined (our holiday definiation.png).

please take a look at attached documents.
Could you help me please.
 

 

2 REPLIES
Erik Cole
Acclaimed Contributor.

Re: holiday definiations in task

Are you sure your project type is using the same regional calendar?

Mahen M
Acclaimed Contributor.

Re: holiday definiations in task

What is the version of PPM you are using?

 

Have you marked holiday first and then created the task and entered the duration days.

 

Or you created the task first, Entered the duration days and then marked holiday in the calendar.

 

I tested in 9.14 and If you follow the first method, everything works fine, if you follow the second method then it isn't working.

 

Must be a defect!

 

Regards,

Mahendran M


Regards,
Mahendran M