hello,
Please help I need an import a Microsoft Project column, to a custom column of PPM work plan, this through the user data.

greetings and thanks!

3 REPLIES
dirkf
Honored Contributor

Re: custom column of PPM work plan 9.14

Hi Pedro,

 

that's not much information.

Please provide an mpp-workplan, let us know what you are trying to import and where to.

 

BR,

Dirk

Pedro_X
Occasional Contributor

Re: custom column of PPM work plan 9.14

Hello,

I uploaded a picture with the column you wish to import the PPM.

greetings and thanks!

 

dirkf
Honored Contributor
Solution

Re: custom column of PPM work plan 9.14

Hi Pedro,

 

in project settings of the corresponding project, you will find a section 'Microsoft Field Mapping'. In that section, you can use an xml-file to map MSP task column data to PPM user data fields.

For an introduction to the creation and usage of the field mapping, please check the Project User Management Guide, page 274 and forward.

I will attach the guide for your reference.

 

Best regards,

Dirk