Hi ALL.
I need set WP to requered in any WF step in project request.How it possible?
I not wont to create it automaticly by executing WF step i.e. have many WP templates.
Many thanks
2 REPLIES
Mahen M
Acclaimed Contributor.

Re: Work Plan set requered in any WF step

Hi Alex,
We too had this requirement of multiple WP Templates

1. 'WP Template Short'
2. 'WP Template Long'
3. 'WP Template Medium'

We are getting the WP Template as an input Parameter from end users according to their requirement and passing this parameter.

We are passing the template ID as a parameter.

ksc_run_java com.kintana.core.server.execution.CreateWorkplan -projectId "[REQ.P.KNTA_PROJECT_PLAN]" -overrideWpTemplateId "[REQD.P.WP_TEMPLATE_ID]"

If you don't want to use the 'executing WF step' at all, then I have no solution.

Regards,
Mahendran M