Good Day.
I use 7.5 sp 3.
I have task: how we can planned misc.works for example "support".
I try use work allocation(WA)but i don't anderstand for wich periods can create this WA. Afret create WA for support set original budget 100 and set user access try add this support misk to my Time Sheet a have expected hours=100.Nex I add 40 hourse per 2 TS but added hourse not appear. It's bug or normal.
Next i chech analize assignment load portlet for my resource and 2 periods but this assignment not appeared. Why?
If WA not allow compare planned and actual, for wich task use this mechanism.