Why some tasks do not show up in time sheet?

SOLVED
Go to solution
Highlighted
TurboMan
Member

Why some tasks do not show up in time sheet?

Hi,

 

We have a workplan, and assigned resources for a task.

In TimeSheet when we try to add that particular task or request, It doesn't come up in the list.

 

Any help is appreicated

 

Regards

TM

2 REPLIES
TurboMan
Member

Re: Why some tasks do not show up in time sheet?

sorry, forgot to mention we use PPM 7.5 SP7

 

Regards

TM

TurboMan
Member
Solution

Re: Why some tasks do not show up in time sheet?

Found,

The Work Plan status was not "Active" it was in the "In Planning" status.

 