Why some tasks do not show up in time sheet?

SOLVED
Go to solution
Highlighted
TurboMan
Honored Contributor.

Why some tasks do not show up in time sheet?

Hi,

 

We have a workplan, and assigned resources for a task.

In TimeSheet when we try to add that particular task or request, It doesn't come up in the list.

 

Any help is appreicated

 

Regards

TM

2 REPLIES
TurboMan
Honored Contributor.

Re: Why some tasks do not show up in time sheet?

sorry, forgot to mention we use PPM 7.5 SP7

 

Regards

TM

TurboMan
Honored Contributor.
Solution

Re: Why some tasks do not show up in time sheet?

Found,

The Work Plan status was not "Active" it was in the "In Planning" status.

 

Regards

TM