Project and Portfolio Management Practitioners Forum
cancel

What is the status_code for -100 in Rsc_resource_Assignment table.

Highlighted
PPMRam
Super Contributor.

What is the status_code for -100 in Rsc_resource_Assignment table.

Hi Team,

 

we are using PPM 8.0,sunsolaris operating system,xp version2.

May i know the status_code meaning for the -100 in the rsc_resource_Assignment table.It is very urgent.Please reply to it.

 

Thanks

Praveen. 

1 REPLY
dirkf
Acclaimed Contributor.

Re: What is the status_code for -100 in Rsc_resource_Assignment table.

Hi Praveen,

 

In the table RSC_RESOURCE_ASSIGNMENTS, the column STATUS_CODE describes The code that represents the status of the resource assignments. The code is decoded by the application to represent the meaning on the UI. The status of the assignment could be soft-booked, committed, and so on

STATUS_CODE -100 should not exist. They start of with 1,2,3,4.. etc. If you have such a status_code, then there’s something wrong with the assignment.

What’s the error (front-end) and stack (serverlog) that you are receiving?

 

Best regards,

Dirk