Project and Portfolio Management Practitioners Forum
cancel
Showing results for 
Search instead for 
Did you mean: 

Webservices in PPM v7.1

Highlighted
Abdullah Rafiq
Regular Collector

Webservices in PPM v7.1

Hi,

Our client would like to update the budget entity without having to manually update these values in PPM. Ideally, they would like to update the budget for a single budget, or a group of budgets in the system.

My thought was that we could give them a microsoft excel template to fill out and have them save it as a comma delimited file. They would then take this file and attach it to a request in PPM where a database function would run, parse through the file and update the necessary budgets.

I've recently heard about the possibility of using HP webservices to accomplish this task. Does anyone have documentation on how to set up and use webservices and some documentation we could use as examples.

Thanks,
Abdullah
2 REPLIES
Vadim Solenyi
Occasional Contributor

Re: Webservices in PPM v7.1

Hi,

We solved a problem of updating of budgets in an automatic mode. Budgets were conducted in external system (Oracle) and daily special procedure updated values in PPM.

Vadim
Abdullah Rafiq
Regular Collector

Re: Webservices in PPM v7.1

Vadim,

Thanks for the reply, I have thought of that solution but thought that webservices may provide a better solution.
//Add this to "OnDomLoad" event