View/portlet/report by resources by project task/activity with cost and time

Hi Guys

I am just trying to List of resources by project task/activity with cost and time

I have got close to this but not quite this list - any ideas?
2 REPLIES
Erik Cole
Honored Contributor

Re: View/portlet/report by resources by project task/activity with cost and time

Gillian,

We wrote our own SQL for this since none of the stock reports or portlets had this. Getting the hours is relatively easy, and is what we did, but getting the actual costs would be somewhat more difficult since these are not stored at the task-assignment level.
Gillian_NZ
Occasional Advisor

Re: View/portlet/report by resources by project task/activity with cost and time

Yes, I came to the same conclusion - which is a shame because it is a pretty standard request and as a minimum you would (hope) it would be at least OOTB portlet functionality.
Thanks for responding