View for displaying only current week task

Highlighted
bsbabu
Super Contributor

View for displaying only current week task

Hi,
Is there any way that we can restrict the team members to see only the tasks that are assigned to them for the current week and pending tasks instead of all incomplete tasks?

Regards,
babu
1 REPLY
Semenov Alexand
Esteemed Contributor

Re: View for displaying only current week task

Hi.
You can use "My task" portlet.
In setting of this portlet set:
-task starting within 7 days from now
or
-task finishing within 7 days from now

Good Luck