Hi,
Is there any way that we can restrict the team members to see only the tasks that are assigned to them for the current week and pending tasks instead of all incomplete tasks?

Regards,
babu
1 REPLY
Semenov Alexand
Acclaimed Contributor.

Re: View for displaying only current week task

Hi.
You can use "My task" portlet.
In setting of this portlet set:
-task starting within 7 days from now
or
-task finishing within 7 days from now