Upgrade PPM from 9.12 to 9.14

We are planning to upgrade PPM from 9.12 to 9.14.

 

Want to ensure that we can move PPM from 9.12 to 9.14 directly, without upgrading to 9.13  as a transition.

 

Judy

4 REPLIES
Jason Nichols K
Acclaimed Contributor.

Re: Upgrade PPM from 9.12 to 9.14

Judy,

Yes, you can apply SP4 without having to apply SP3 first. All the fixes inSP3 are included in SP4.

Jason
Oscar_Pereira
Honored Contributor.

Re: Upgrade PPM from 9.12 to 9.14

Hello Judy,

 

I strongly recommend to also install one of the  latest mini-patches for Service Pack 4.

 

A few weeks ago HP released the last patch  0004,  you need to first install the SP4 and on top of this, you can install the 0004.

 

Thanks

Oscar Pereira

 

 

 

Toby Harvey
Respected Contributor.

Re: Upgrade PPM from 9.12 to 9.14

Hi Judy - I can confirm I went direct from 9.10 to 9.14 without problems and have also applied the 0004 patch that Oscar mentioned ...

Alexander (Sua)
Super Contributor.

Re: Upgrade PPM from 9.12 to 9.14

Hi Judy

Some time ago we also moved from 9.12 to 9.14 and 9.14.003 at the same time.

we met just one problem ....

While PPM migrating doc to its own DMS documents are blocked for reading|changing. That's why we implement migrating documents from file system to DMS on a weekend

 