Upgrade PPM 7.5 to 8

Highlighted

Upgrade PPM 7.5 to 8

Have already anyone finish this kind of upgrade? And if yes, what were some "gotchas"?
Eventually some hints and tips for this please.
thanks a lot
rgds
Vladimir
1 REPLY
Alexandru Saven
Regular Collector

Re: Upgrade PPM 7.5 to 8

Hello, Vladimir,

I managed to perform an upgrade from 7.5 SP4 to 8.

the (main) problem was related to custom scoring keys - it looks like the upgrade kits is hardcoded with seeded values for scoring keys...

I overcame this issue by removing the custom scoring keys in 7.5 and re-applying them in 8.0.

good luck :)

Alex