Updating work plan from MS Project

Good Day.
I use 7.5. sp3.
I have an project with work plan created from PPM directly. Also I use Time Management to reporting time to task.
Question: I need upgrade work plan from MSP (add approximately 400 tasks). How it possible
Thanks in advice.
3 REPLIES
Erik Cole_1
Outstanding Contributor.
Solution

Re: Updating work plan from MS Project

Two ways I can think of offhand:

(1) change your project's MSP integration to 'Shared', download the workplan to MSP, add your new tasks there, upload back to PPM, reset integration to 'PPM'

(2) create a dummy project without a workplan, upload the new tasks to this project from MSP; in your original (target) project's workplan highlight the last task, click Actions -> Import another workplan and select the one on the dummy project.
Semenov Alexand
Acclaimed Contributor.

Re: Updating work plan from MS Project

Erik,Many Thanks.
All working fine.
Semenov Alexand
Acclaimed Contributor.

Re: Updating work plan from MS Project

Case 2.