Update staffing profile from updated work plan

I am trying to find a users easier way to update a staffing profile when the workplan - schedule has been updated? Is there a way to at least get both sets of data on the same page?

I would also like to know the back end way to accomplish this if an user way is not available.

thanks so much,
Katherine
2 REPLIES
Canturk G TOPRA
Valued Contributor.

Re: Update staffing profile from updated work plan

Hi,

You can use "Compare to WorkPlan" option in Staffing Profile or "Resource Usage" option in WorkPlan. This will give what you need.

Regards
Katherine Montr
New Member.

Re: Update staffing profile from updated work plan

Sorry - I may have not been detailed enough. Once I get my true scheduled hours updated from the original and compare it to the workplan, I want to change/update the individual resources to what the new scheduled effort is. Did that make sense?