Tracks capital costs in HPPPM 8.0

Highlighted
Prabha N
Super Collector

Tracks capital costs in HPPPM 8.0

Hi All,

We like to keep "The proposal is for a project that tracks capital costs" enabled all time in Financial Summary settings.
How can we acheive this?

Thanks,
Prabha
2 REPLIES
Mahen M
Honored Contributor

Re: Tracks capital costs in HPPPM 8.0

Hi,
The Project's Financial Summary Settings are loaded from Project Type -> Cost and effort -> Financial Management.

There is no such thing called Proposal Type, and there seems to be no area whether we can set the default values for Proposal's Financial Summary settings.

Perhaps you can try enable it by updating the table through query or webservice.

Regards,
Mahendran M
Mahen M
Honored Contributor

Re: Tracks capital costs in HPPPM 8.0

Yes, I am right.... got confirmation from HP.