To automatically populate the Task User Data fields with project fields

Highlighted
JudyZhu
Super Contributor.

To automatically populate the Task User Data fields with project fields

Our customer requested to automatically populate Task User Data fields with related project fields when to integrate with Sm RFC.


It seems that request type rules do not cover Task User Data.

 

Is there any other way to fulfill this request?

1 REPLY
Celil
Acclaimed Contributor.

Re: To automatically populate the Task User Data fields with project fields

Hi Judy,

 

Even if I couldn't understand when it triger but you can do it with calling a DB function which update Task User Data field in DB Table.

 

PS: If the post resolves your issue, please click KUDOS star icon and mark it as Accepted Solution.

 

Celil

IT Governance Professional