Good Day ALL.
I have an question:
Why time from TS logged to tasks in work plan before approving TS. Can I change this setting?How?
Thanks in advice!!!!!!!!!
2 REPLIES
Sangiliraja_1
Honored Contributor.

Re: Time Sheet actual effort

Hi,

That is a intented implementation in PPM. This is mainly used by PM's to track the progress of plan as well before approving the time. If Manager is not fine with the progress of the plan he/she can reject the timesheet and thus rolling back the plan progress.

As soon as resource has a time sheet with time, it gets shown up in PPM plan and PM's can see that this many hours have been entered for the task. Now he can as well see the progress of whole plan and based on PM's wish can approve or reject to make time pertain or rolled back.

Thanks
Sangiliraja.P
Aravinth
Respected Contributor.

Re: Time Sheet actual effort

Hi,

To add to earlier post , this setting cannot be changed. As a best practice, it is suggested to the customer to put a process in place and ask users to put in time on a particular ay of the time period configured.
Thanks,
Aravinth