Hi,

I am trying to enable time management for projects. As required, i was having project setting accordingly.
1. Project to have time tracked at project level
2. All project reseources can track time.

When i get the time entry from a resouce, it capture only effort. Actual start and end dates are not captured. So the project plan progress remains as 0 eventhough there are actuals.

Does anyone have faced this issue before resolved it.

 

I am using ppm 9.31