Task assignment day-by-day

Highlighted
Edoardo Spelta_
Respected Contributor.

Task assignment day-by-day

Hello,

is it possibile, when planning the effort needed for a resource to complete a task in a project, to specify the exact days when the resource will be allocated ? As far as i understood, the effort is always evenly distributed among the task start/end dates, is it true ? Is there any workaround to this ?

Has anyone found a way to plan the effort of resources at a more granular level ? Maybe directly updating the tables in the database ? After all, the capacity/workload graphs in the resource profile pages show the effort on a dayly basis. From where these values come from ?

I'm working on PPMv8/9