Task Assignment error

Highlighted
KartikSharma
New Member.

Task Assignment error

Hi,

 

I am currently working on PPM 9.1 and I am facing an error while changing the 'Scheduled Start' date for a task in workplan of a project from view Work Plan page.

However, when I change the 'Scheduled Start' date from Task Deatils page, I get no error and the change is reflected in the work plan.

 

The task that I am trying to chane the 'Schedule Start'ate for is 'In Progress' and the workplan is 'Active'. Also, the Project is yet not completed.

 

Please help me on this issue with your suggestions and pointers.

 

Thanks in Advance..!!

 

Thanks,

Kartik

3 REPLIES
Utkarsh_Mishra
Acclaimed Contributor.

Re: Task Assignment error

Try to remove the actuals in "Define task" task and then proceed.

Cheers..
Utkarsh Mishra

-- Remember to give Kudos to answers! (click the KUDOS star)
KartikSharma
New Member.

Re: Task Assignment error

Hi Utkarsh,

 

Thanks for the update.

 

However, I am afraid that I cannot clear the actuals of a running project.

Also, the actuals in the 'Unassigned Effort' is uneditable.

 

Adding more on this, I am not sure why the 'Schedule Start' is getting updated when I try from Task Details page but not from Work Plan Deatils page though the actuals are present in both scenarios.

 

Please update accordingly.

 

Thanks,

Kartik

Celil
Acclaimed Contributor.

Re: Task Assignment error

Hi Kartik,

 

I think it's a bug. You should can't change sch start date even in details.

 

To remove actuals you should delete related time sheet lines. First of all find resources, find their time sheets and delete releated lines.

 

PS: Please keep alive our forum via kudos the professionals

Celil