Stopping Timesheets when project is complete

Highlighted
Ryan Grobler
Regular Collector

Stopping Timesheets when project is complete

Hi All

Is there a setting which sets a workplan to 'complete' when a project gets closed?
1 REPLY
Sascha Mohr
Esteemed Contributor

Re: Stopping Timesheets when project is complete

Yes, you need an execution step in the project's workflow that executes this command:
ksc_update_workplan_status STATUS="COMPLETE"
//Add this to "OnDomLoad" event