Service to update Budgets and Staffing Profiles not running on stage.

Hi All,

How can we confirm that services to upddate Budget and staffing profile in PPM not running as scheduled . Users are complaining that their Budgets and Staffing profile are not being updated by more than 36 hrs or more...How can we check from our end whether services are running or not as scheduled .If services are OK? what could be other reasons for particular budget or staffing profile.

Thanks,
Phani
1 REPLY
Erik Cole
Acclaimed Contributor.

Re: Service to update Budgets and Staffing Profiles not running on stage.

Workbench > Sys Admin > Server Tools > Service Controller Report

This will give you the last run times and the intervals (usually in seconds) they are set to run.