Scheduled effort in person-days

Highlighted
AlekseyG
Super Contributor.

Scheduled effort in person-days

Hello!

I wonder if it's possible to track scheduled effort for tasks in person-days instead of in hours?

1 REPLY
dirkf
Acclaimed Contributor.

Re: Scheduled effort in person-days

Hi Rosbank,

 

is possible :-)

Check the following BUT make sure you understand that these parameters take effect on several places. Test this first to see that you can use it everywhere.

 

The following parameters can be used, especially the second one is what you are looking for:

 

RM_ALLOWED_EFFORT_TYPES

Determines the effort types allowed for HP Resource Management staffing profile and other modules. You can specify a combination of up to three comma-delimited values.

Examples

 fte, person_days, hours

 fte, person_days

 fte, hours

 person_days, hours

The order does not matter.

Default: fte, person_days

Valid values: hours, fte, person_days

 

RM_DEFAULT_EFFORT_TYPE

Effort type used to display staffing profiles and resource pool information.

Default: fte

Valid values: hours, fte, person_days

 

Appreciate setting this thread to solved if you find that you have your information.

 