Resources with Scheduled hours (more than 999) gives error on Save.

Highlighted
Niraj Prabhu
Outstanding Contributor.

Resources with Scheduled hours (more than 999) gives error on Save.

Hi,

 

We have resources to be tracked on our PFM - Proposal form. When the resource is scheduled with more than 999 hours (eg. 1100), the Resources table component shows scheduled hours as (1,100). Once clicked save again, the error message appear which says, "The field Scheduled Effort(hrs) should contain only numeric characters or decimal separator"


This happens for all Users, and they aren't specifying the effort with any commas; they provide only numbers in the scheduled effort and the system defaults the commas after first save/workflow action. Error appears if user click save again with effort more than 999.

 

Niraj P.
1 REPLY
PPM09
Contributor.

Re: Resources with Scheduled hours (more than 999) gives error on Save.

we are having same issue. Do you have any solution?