Project and Portfolio Management Practitioners Forum
cancel

Resources in the task list

Highlighted
Mohit_Agrawal
Outstanding Contributor.

Resources in the task list

Hi All,

 

I can see that some resources that are not in the staffing profile but they are available to me for selection in the resources list on a task in the work plna.

 

What all users get listed there? is there any defined criteria?

 

 

 

 

Thanks

1 REPLY
Tim_Brandish
Respected Contributor.

Re: Resources in the task list

Check the server.conf setting com.kintana.core.server.RM_OVERRIDE_ASSIGNMENT_CONTROLS.  If it is set to true, you are able to assign resources not listed in the staffing profile.