Resources dropped from resouce pool when added to another

Highlighted
Scott A. Wood
Trusted Contributor.

Resources dropped from resouce pool when added to another

When a resource is added to a resouce pool (using the Manage Pool Capacity) they are automatically added at 100% and dropped from any other resource pools that they are in. There are no warning messages displayed to the person maintaining the resouce pool. This situation is causign an issue.

Are there any settings that can be changed to warn the PM that the resouce is currently assigned to a differenet resouce pool? If this has been a problem for you, how have you handled it?

We are using PPM 7.1 SP8.

Thanks,

Scott