Resources Could Not Be Scheduled

Highlighted
Rafe Garet
Occasional Advisor

Resources Could Not Be Scheduled

I am receiving the following error on some of my tasks:

This task requires that one of the assigned resources be available to schedule task work on a given day. The following resources are not available for sufficient numbers of working days to meet this requirement for this task, which has a duration of 385.0 day(s) starting Jun 23, 2008. Resources were ignored during scheduling: . You should verify that the start and end dates for all resources and their calendars are valid for the time period of the task.

I have verified the start and end dates for all of the resources are OK. Is there any explanation for this error?
2 REPLIES
Semenov Alexand
Esteemed Contributor

Re: Resources Could Not Be Scheduled

Hi
May be this resource not in resource pool?
Rafe Garet
Occasional Advisor

Re: Resources Could Not Be Scheduled

That's not the problem. I checked and resource is in resource pool during the dates for the task
//Add this to "OnDomLoad" event