Resource changing Resource Pool

I want to know what would happen to the Allocations in the Resource Pool when a resource shifts from one resource pool to the other.
2 REPLIES
Varun Singh
Respected Contributor.

Re: Resource changing Resource Pool

Hi Raka,

When an another resource pool manager assign a resource which is already present in the other existing resource pool, he selects the start date of that resource in the resource pool. It also has the option of % participation column. If the participation is 100% then the assignment of the resource ends one day previous to the selected data in perivious resouce pool, that means assignment in the previous resource pool ends. and starts in new resource pool.

Hope it help

thanks
Varun
Arguing with a fool, proves there are two
mcmunnd1
Respected Contributor.

Re: Resource changing Resource Pool

However, the work that was already allocated to that resource from the original resource pool will stay allocated to that resource in that original resource pool.