Resource calender in HP PPM

How can I define resource calender so that the holidays and leaves can be assigned to the resource. Also is the Region calender and the resource calender if created will they be taken into account while creating the tasks in HP PPM tasks module.
2 REPLIES
Semenov Alexand
Acclaimed Contributor.
Solution

Re: Resource calender in HP PPM

Hi.
Resources have a personal calendar in additional to regional calendar. Search resource, go to tab Calendar. In this page you can edit working and non-workink days and set reason.
Dana G Smith
Valued Contributor.

Re: Resource calender in HP PPM

To answer your question about calendars taking into effect when assigning tasks, yes. The resource availability is decremented with the non-working days (hrs) from the calendars.