Resource Calendar Update HP PPM

Highlighted
Vsalian
Regular Collector

Resource Calendar Update HP PPM

Hi,

Our Resource calendar only goes till Sep 2011.
How do i go about updating it?
I cant select dates beyond Sep 2011 when creating a staffing profile. I would like it to extend till Sep 2015.
Any help would be much appreciated.

Thanks,

V
2 REPLIES
shygirl
Regular Collector

Re: Resource Calendar Update HP PPM

For PPM8, the staffing profile periods uses a validation PFM - Periods by Month. You can check the validation_sql to see the query. To generate periods, i think you should use kGenFiscalPeriods.sh or kGenPeriods.sh.

Vsalian
Regular Collector

Re: Resource Calendar Update HP PPM

Thanks for your response...But I am a newbie to this and didnt get much out of your response. I have attached a screenshot which shows Finish period as 2013 but the calendar only extends till Sp 2011. How do i fix this?? See attached

Thanks again