Resource Availability View(s) in PPM

Highlighted
Scott Scoggins
Contributor.

Resource Availability View(s) in PPM

How can I view overall resource availability in PPM? I can't find good information in the manual for resource management.
1 REPLY
Sevilay
Honored Contributor.

Re: Resource Availability View(s) in PPM

Hi Scott,

did you try the "Analyze Assginment Load" system portlet.You can configure it and can see the details at the project and satffing profiles levels.