Hello All
I am new to the PPMC.
We need to make some reports (we use Crystal Report as the basic tool). I found the document - Report MEta Layer

It is a pitty but there is no RML for Projects as i have red from the RML document, but it was in version 6.
I need to select tasks (milestones) from the particular project. Can somebody help, what tables should i use ?

Rgs, Vasily Aksenov
5 REPLIES
Alessandro Baio
Trusted Contributor.
Solution

Re: Reporting from PPMC

Hi Vasily,

speaking about PPM 7.1, you can look up for tasks in the "WP_Tasks" table, whereas projects are in the "PM_Projects" table.
Workplans and baselines are in the "PM_Work_Plan" table.
You can find detailed information about the data model in the "Technical Reference Manual".

Regards,
alessandro
Vasily Aksenov
Acclaimed Contributor.

Re: Reporting from PPMC

Thanks!
I downloaded this document from HP site, but it is corrupted.
If it is possible, can you send me by e-mail
"Technical Reference Manual".

ospkpp@sbrf.ru
thanks in advance

Best Regards, Vasily Aksenov

Alessandro Baio
Trusted Contributor.

Re: Reporting from PPMC

Hi,

the Technical Reference Manual is a huge document (about 4,5 mb), I downloaded it from:
http://support.openview.hp.com/selfsolve/document/KM248463/binary/PPM_Center-PPM_v7.1-TRM_pdf

I've also had problem in download some documents, but after a few trials I succeded.

Let me know,
Best Regards.
alessandro
Vasily Aksenov
Acclaimed Contributor.

Re: Reporting from PPMC

HI
i have downloaded and opened document after several attempts.
thanks it is what i needed.