Reload the previous workplan baseline

Highlighted
Jorge Avendano
Super Collector

Reload the previous workplan baseline

I need reload the previous workplan saved in a baseline in a project. Is this possible??? I have enabled a previous baseline but the project continue show me the last baseline saved.

Somebody has any idea about how reload previous baseline??

Thank you!!!
1 REPLY
Shilpesh Pathak
Acclaimed Contributor

Re: Reload the previous workplan baseline

Hi Jorge,

Baseline is the snapshot of a Workplan at a perticular stage of a project and this functionality is used mainly to compare the project status at various stages of its lifecycle.
And it is not possible to reload the Workplan template, If you enable the Baseline then you can use it to compare it with what you have in your current Workplan.

Regards,
Shilpesh Pathak