I have a WBS template with url links in the references section. When I create a new work plan based on the template, the references are OK. When I import a template into an existing WBS using the same template, the references are lost. Has anyone seen this behavior before? Is there a fix for this?
2 REPLIES
Peter Manzari
Acclaimed Contributor

Re: References on WBS Templates lost on import

On a related issue, I also discovered that when you Cut and Paste a task the References are carried over. However, when you Copy and Paste a task, they are not.
Rafe Garet
Occasional Advisor

Re: References on WBS Templates lost on import

Submitted Incident with HP