Project mgt and time mgt integration

Highlighted
Manas Bagde
Trusted Contributor.

Project mgt and time mgt integration

Hi All,

I have created a project, workplan and staffing profile for the same project. Workplan is in ACTIVE status and all the tasks are in READY status.

From staffing profile i have requested resources to resource pool.
Resource pool manager has approved my staffing request.
Assigned resources to my work plan task.
From time management i have filled actuals against project task.

Now the issue is i am not able to see the acutals in my project workplan task. Could you please let me know whether i am missing anything here.

I am attaching gif file of "Cost and Effort" tab of Project Type policies.

Regards,
Manas
2 REPLIES
Celil
Acclaimed Contributor.

Re: Project mgt and time mgt integration

Hi Manas,

For projects that are integrated with HP Time Management, after users
enter actual effort for tasks on the Time Breakdown tab, the time sheet update
service (TM-PM Sync Service) sends updates of that actual effort to the project work
plans for those tasks, as often as specified by the service (by default, every 3 hours).

Celil
Celil

IT Governance Professional
& PPM Solution Architect
Manas Bagde
Trusted Contributor.

Re: Project mgt and time mgt integration

Thanks Celil. This issue is resolved