Project Plan weekend tasks

Highlighted
Scott A. Wood
Trusted Contributor.

Project Plan weekend tasks

In PPM 7.1 SP8 we want to have two project tasks start and end on a weekend days but do not want to have a separate region & calendar for this activity. Is this possible? I can force the tasks to start on Saturday, but then the end date changes to Monday.

Thanks.