Project Current Cost Metrics portlet

SOLVED
Go to solution
Highlighted
Sandeep K
Super Collector

Project Current Cost Metrics portlet

Hello,
The Project Current Cost Metrics portlet is not showing any financial data for a selected project.
The project has an active budget and also has Financial Management enabled under Cost and Effort section under Project settings.
And the logged in user is an admin who has access to view all budgets.

However could one of these 2 be causing the issue ?
1.The budget is set to manually enter planned and actual values.
2.The workplan has no time charged to it yet.

But shouldn't the budget data show up at least ?

We are on v7.1 SP8.

--Sandeep.
3 REPLIES
Erik Cole_1
Esteemed Contributor
Solution

Re: Project Current Cost Metrics portlet

Hi Sandeep,

I think you need to have a baseline workplan.
Sandeep K
Super Collector

Re: Project Current Cost Metrics portlet

Erik,

That did the trick !! Thanks a ton!