Program Risk, Issue, Change health indicator

Highlighted
john.jeremiah
Trusted Contributor.

Program Risk, Issue, Change health indicator

In the Program Settings page, there is a configuration setting for the indicators to go yellow (20), and Red (40)... based on the sum of the program's risk..

From the Program Setting page for Program risk:
"The Risk Health of the program is determined by adding up the weights of all of the program's risk. Below you can specify the weight for the risk, based on its impact and probability."

I've set the risk health value to 0, 1, and 10, but cannot get the indicator to change from green.

Does anyone know where are the weights for thes values are set?
1 REPLY
Sascha Mohr
Acclaimed Contributor.

Re: Program Risk, Issue, Change health indicator

I would be interested in that too. I just created a single risk request for a certain project and the risk indicator for the program it is associated with went to red immediately.
We usually don't use tracking of risks on program level, but sooner or later someone will ask for this too.