Program Critical Path

Dear Community,

We have a Program with 6 dedicated Project Plans linked to it. Each Project Plan consist of approximatelly 300 Tasks. Project plans interlinked using external dependencies between the Tasks.

We can easily see Critical Paths of each individual Project plan in Workbench. But this doesn't give us understanding of the Program Critical Path.

Question:
Is it possible to see Critical Path of the whole Program shchedule? Like if you join all these 6 Project plans togetehr into one huge 1800 tasks Project plan and check it Critical path?